Town Administrator Karl Kilduff asked Weston's Board of Finance on Thursday, Nov. 12, to pay for a smaller Valley Forge Road project he could not yet show it. "I don't have an actual drawing because I don't have funding," he said.
The board then approved $76,000 for the town's engineers to draw one and take it through state review. The goal is a design that stays within the existing pavement and off private property. The town hopes it will keep a state grant of more than $5 million that pays for most of the job.
The vote was 4-2, a month after the selectmen backed the redesign. The money is $31,000 moved from the finished Lyons Plains Road project and $45,000 in new money. Members Annalise Ferrara and James Aselta voted no. The same night, the board split 3-3 on last year's budget transfers and will take them up again next month.
The grant comes from the state's LOTCIP program, under which the state pays to build a local road project and the town pays for its design. The design being replaced grew out of the state's feedback. It would have widened the road and added drainage work that needed temporary and permanent easements on private property, Kilduff told the board, and "it was clear" those would be hard to get. Two residents of the road asked the board on Oct. 29 to see a scope of work and a timeline before it paid for more design.
The new design would reduce or drop the drainage work, Kilduff said. It still has to give the road surface a 20-year life, as the grant program requires, so it will be "more involved than a simple mill and pave." Asked by Ferrara whether the work would stay within the roadway, he said that is the design concept.
"Whether you're for the project or against it, there is a consensus that the road needs to be paved," Kilduff said. Chair Michael Imber said the question was "do we want the state to pay for it." Without the grant, he said, the town would have to borrow the several million dollars the road needs.
Ferrara's objection was to where the $31,000 comes from. She told the board that a stretch of old fence along Lyons Plains Road had not been replaced, and she wanted Kilduff to confirm the project was finished before its leftover money went elsewhere. Her amendment to wait for that answer, seconded by Aselta, failed 2-4.
Earlier in the meeting, the board voted 5-1 to move another $29,000 from Lyons Plains Road to test the soil at the Public Works garage, where a heating oil tank leaked in 1989 and the case was never closed with the state. Ferrara's amendment to hold that money until the fence question was answered got no second. Kilduff's Oct. 13 memo says the Lyons Plains project has been closed out with about $60,000 left. The two votes moved $60,000 of it.
"Hopefully it's just poor record keeping and the town did the right thing after 2000, but we don't know that," Kilduff said of the oil leak. The borings would take a couple of weeks, he said, and the tank at Public Works has to be out of the ground by September 2027.
A 3-3 tie on last year's budget
The tie leaves the town's line-item transfers for the 2025-26 fiscal year unapproved, after they stalled at the Board of Selectmen in October. The transfers move money from accounts that finished the year with money left over to accounts that ran over. Finance Director Richard Darling said the town departments' budget ended the year $186,403 under. General government was the problem area, he said, because of health insurance, electricity and legal costs. Imber put its overrun at about $41,000, the only major area in deficit.
"These transfers are nothing more than accounting movements," Imber said, and the town did not spend more than voters approved. Member Daniel Gershburg called the dispute "a solution looking for a problem."
Vice Chair Alex Staehely, Ferrara and Aselta argued that departments should come to the board before they overspend, not five months later. Ferrara said the town charter requires such transfers within three months of the end of the fiscal year. She also asked who approved spending on the attorney for the charter revision, which she put at about $72,000, and said no one had brought it to the board. Darling said the legal budget finished about $39,000 over, nearly all of it for that attorney.
Aselta pointed to Section 9.10(d) of the charter. "The charter is not a guideline," he said. "It's basically our constitution." Imber said the town has a legal opinion that doing the transfers after the year closes is legitimate, and that about half the towns in the state do it this way, according to the town's auditors. Aselta asked that the auditors come to next month's meeting.
Also at the meeting
- Darling's first-quarter report projects town revenue $728,000 over budget, mostly because a planned tax sale was called off when every taxpayer on the list paid. He projected an unassigned fund balance of about $19.2 million, about 22.5% of this year's budget, built on last year's still-unaudited books.
- Phillip Cross, the school district's chief finance and operations officer, said the schools will go over budget on health insurance because more people signed up, and that the district won a competitive state grant of about $124,000 for special education.