Thomas Shea pointed his colleagues to page 36 of the engineering report for the North House at Hurlbutt Elementary School. "Construction contingencies are not included," Shea, a member of Weston's Building Committee since October, told them on Wednesday, Nov. 4. The $2.4 million estimate to replace the building's heating and cooling, he said, sets nothing aside for problems that turn up once work starts.
Shea spent 25 years in finance. The estimate does carry a 10 percent contingency for design, he said, adding, "I would think that construction contingency would be a much bigger contingency than design." If it meant another $500,000, "that's a big deal." Another member suggested the design contingency might already cover it.
Megan Loucas, the committee's chair and a licensed architect, said she would send the members' questions to Phillip Cross, the school district's chief finance and operations officer, and Michael DelMastro, its director of facilities. No one from the schools attended, she said. The project is "somewhat out of everyone's wheelhouse since no one here is a mechanical engineer," Loucas said, so the committee's job is to review the documents and advise.
North House heating and cooling
In January, Cross told the Board of Finance that the North House's mechanical systems had reached the end of their useful life. Its classrooms "routinely experience uneven heating, limited cooling and humidity control issues," the board's minutes say. Greg Russo, a committee member who said DelMastro had shown him through the building, said he was told the floors "get really wet and moist, especially in the gym."
The district chose the third of the report's options: wall-mounted units that both heat and cool, called ductless mini-splits, in the classrooms; a ducted system bringing fresh air into every room; and a refreshed system for the gym. The members want to know whether the classrooms' old heating units stay as a backup, as Loucas read the demolition drawings, or come out, as Russo understood from DelMastro, and whether the roof can carry the outdoor equipment.
Hurlbutt HVAC money and oversight
The Board of Finance approved $600,000 for the project on Jan. 8, and the selectmen approved it Jan. 15. The money was needed to place a purchase deposit by February for work to start in early June, the finance board's minutes say. In May, the selectmen recommended borrowing up to $1.4 million more and called a Special Town Meeting for June 23. Their October resolution says a Special Town Meeting approved the bond authorization.
That resolution, passed Oct. 15, created a Hurlbutt Elementary School HVAC Building Committee: the Building Committee's seven seats plus the school board chair or a designee. The resolution says the town needs a committee that meets state rules to receive state money for the work, through an indoor air quality grant. That committee must approve any change orders, the changes made to approved plans once a job is underway, and it can approve them only within the project's total appropriation.
Two of the Building Committee's seven seats are vacant, according to the town's website.